領(lǐng)順為你介紹冷庫的安裝方案
1 地板安裝
先把地坪找平,后開始按裝地板,挑選美觀的地板放于顯眼處,并做好地板及蒸發(fā)器排水系統(tǒng)。
質(zhì)量要求:
地板安裝平整,不平處用材料把地坪墊平,并鎖緊板與板之間鎖鉤,達到庫面平整,無空心感。(注意此排水系統(tǒng)如庫體安裝于北方室外則排水管需保溫)。
2 立板安裝
根據(jù)場地情況先選一角,并定位(即立板與地板鎖緊)以此角向兩邊延伸,只把立板與立板間鎖緊,遇到立角處就定位,美觀的板放于顯眼處,安裝到蒸發(fā)器那一面時,預(yù)先把排水管做好,庫外需做 U 型彎及打硅膠。
質(zhì)量要求 :
立板顯眼面平整,庫板無凹點,立板上頭面平齊,立板與立板間縫隙均勻,顯眼處立角與地板角平齊。
3.天板安裝
先選定一頭定位天角板和延伸鋪設(shè),天板與天板間鎖緊,安裝時顯眼一頭天板與立板在保證平整并鎖緊,以防跑位。
質(zhì)量要求 :
顯眼處天板選用美觀天板,天與立板接縫處要平齊、縫隙小,庫里面天板之間平整。
天、地、立板大體安裝好后,天與立、立與地板之間修正平齊并鎖緊,彼此間所有鎖鉤。
遇到需要鋸的庫板,鋸口處需打磨,無毛刺,遇到需拉角鋁的庫板,則先硅膠,再拉角鋁,保證密封性。
庫體安裝好后,排時間打硅膠,硅膠縫光潔、平滑,打硅膠最好排在當(dāng)天收工時處理,以防碰壞。
4.設(shè)備安裝
根據(jù)施工圖及現(xiàn)場了解確定的情況,進行設(shè)備安裝。
Linshun to introduce you to the installation of cold storage 1 floor installation, first leveling the floor, then began to press the installation of the floor, select a beautiful floor in a conspicuous place, and do a good job of floor and evaporator drainage system. Quality requirements: Floor installation level, uneven use of materials to level the floor pad, and locking plate and plate between the lock Hook, to level the warehouse surface, no hollow feeling. Note that this drainage system shall be insulated if the reservoir body is installed outside the north. 2 vertical plate installation, according to the site conditions first select a corner, and positioning (namely the floor and floor locking) to extend to both sides of this angle, only the vertical plate and the vertical plate locking, meet the corner position, beautiful plate placed in a conspicuous place, installed to the evaporator that side, the drainage pipe to do a good job in advance, outside the library to do U Bend and play Silica Gel. Quality Requirements: The prominent surface of the vertical plate is flat, there is no concave point on the warehouse plate, the head surface of the vertical plate is even, the gap between the vertical plate and the vertical plate is even, the prominent vertical angle is even with the floor angle. 3. For the installation of the ceiling, first select one end to locate the angle of the ceiling and extend the paving, the ceiling and the ceiling are locked, and when the installation is carried out, one end of the ceiling and the vertical board are kept flat and locked to prevent the running. Quality Requirements: eye-catching part of the ceiling to choose a beautiful ceiling, the sky and vertical joints to level off, small gaps, the library between the ceiling. The Sky, the ground, the vertical plate is installed, the sky and the vertical, the vertical and the floor between the correction level and lock, each other all lock hook. Meet the need to saw the library board, SAWS TO BE POLISHED, no Burr, meet the library board to pull angle aluminum, first Silica Gel, and then pull angle aluminum, to ensure sealing. After the installation of the library, row time to play Silica Gel, Silica Gel sewing smooth, smooth, Silica Gel best row at the end of the day to deal with, in case of damage. 4. Equipment installation according to the construction drawings and site to determine the situation, the installation of equipment.